Subsea Manifold Installation Project
SAL Heavy Lift's investments in upgrading MV "Lone" to DP 2 class were rewarded during the first DP 2 offshore project: the vessel, crew and DP system all performed superbly.
Two structures were loaded, transported to the field and deployed to the seabed: a protection cover of 80 mtons was loaded in Ortona, Italy. The second structure, a Pipeline End Manifold (PLEM) weighing 120 mtons, was loaded in Limassol, Cyprus.
During the deployment and installation process, the MV "Lone" was supported by the client's diving support vessel (DSV): Divers were deployed from the DSV to the sea bed to assist with structure positioning and de-rigging once the structures had been accurately placed on the seabed.
Source : https://www.youtube.com/watch?feature=player_embedded&v=FjJjWJNWfI8